For the use of electricity service, select a company which has a valid electric work license first and let it perform indoor wiring work. After that, apply for the use of electricity to any branch offices of KEPCO with required documents.
How to apply
- by visit, mail or fax (A staff of electric work company can also apply on behalf of customers if requested)
- by Internet application in the Cyber Branch office of KEPCO.
(Residential service classification or below the 5kw contract demand)
Required Documents
Less than 5kW (residential etc) |
|
---|---|
More than 6kW of contract power |
|
- In case KEPCO performs the inspection prior to use, submit the application for inspection prior to use and the single line diagram(indoor wiring drawing) together with the electricity use application three days before the preferred inspection date. A copy of the business registration certificate and the certificate of completion of inspection prior to use should be submitted before using electricity. You may also present a copy of your ID card or business registration certificate of the other place using electricity (when relocation the business). However, business registration certificates should be submitted immediately upon issuance, Agricultural Well (groundwater) : Submit the groundwater development report (certificate) from the mayor or the governor and the land ledger.
- In case of reapplication after canceling the existing electricity use application, submit a new electricity use application form though there is no change.
Construction Cost
For the electricity use application, the standard construction cost is generally applied except in for special cases (note that indoor wiring work cost is not inclusive.).
Service Start
- The supply of power to the existing facilities may be completed within 24 hours. In case outside wiring is necessary, KEPCO shall supply power on the date indicated by the customer.
- However, in case supplying power electricity cannot be achieved within the customer’s preferred date due to special reasons, specific reasons and available dates shall be notified to the customer.
- For customers supplied with undergourd cabling, however, the schedule shall be fixed after the consultation with the customer.
- High capacity buildings or factories may be supplied with electricity upon consultation with KEPCO during the new/extension plan stage.